HOW TO BUILD HOUSE STEP BY STEP
Ensure that the project is feasible correctly and
legally
In the town where you want to settle, the town hall can inform you about the construct ability and the conditions of servicing your land. You will be able to consult the local town planning plan and request an operational town planning certificate.
Not all land is constructional.
But it is always possible to submit a request for modification or revision of
the local urban plan to the town hall of the town where you want to build. If
no natural risk (flood, avalanche, landslide) on the plot in question is to be
deplored, you have more reason to hope to be able to make a building land. The
prevention plan for foreseeable natural risks annexed to the PLU can prohibit
construction.
The law now makes the study of
the soil compulsory. The seller's responsibility is to provide this
geotechnical study as an annex to the promise to sell. The measure ensures the
stability and durability of the house. A way to avoid cracks, infiltration or
even differential settlement.
To build a detached house, you
can call on contractors (including architects) or builders. However, the types
of contracts that each offers offer very different guarantees that you should
be aware of when choosing. Unlike the individual house construction contract
regulated by the law of December 19, 1990, the project management contract is
only regulated by a standard. The work's final price and that of the services
not included are not specified in the CMO. While the CCMI proposed by the
builders engages their responsibility and notably guarantees the completion of
the construction (even in the event of bankruptcy) at the price and time
agreed.
With the individual house
contract, the builder sells you the product that is the completed house. You
pay him the full bill for your future home. CCMI is more suitable for
standardized houses.
The project management contract
(or architect) is more of a service contract where the designer is independent and
the craftsmen who realize the house. In this case, the project manager
represents you, advises you, and defends you if necessary. The CMO will have
the advantage of sometimes being more competitive for custom homes.
Estimate the cost of construction
Depending on the area, layout,
and materials you determined earlier, you can estimate a fairly wide price
range for your project. Be aware that some construction options such as
choosing a two-story house or a flat roof can increase the price per square
meter.
Design your house
Choose a construction professional
When you want to build your home,
it is strongly recommended that you call on a professional in the sector,
whether a home builder, architect, or project manager. If your house is more
than 150 m², the law requires the presence of an architect for the rest of the
project.
You can check the manufacturer's
notoriety on the internet, social networks, or more simply word of mouth from
professionals and individuals. Or even get in touch directly with those who
interest you to learn more about their working methods, their homes' overall
quality, and the materials they use. If possible, compare the constructions
already carried out by the builder, both in terms of quantity and quality of
buildings.
The "top builder" of
the AAMOI (Association of Assistance to Individual Project Owners) can help
you. It identifies home builders who are often pinned down for irregularities
in the construction contract.
Please note, there can be big
differences between works supervisors of the same construction group. Also,
manufacturers sometimes have their information sites on the web. We must therefore
be wary of their bias.
Small artisans can be as serious
in monitoring their sites as large builders. And this even if some sales
representatives of these large entities sometimes claim the opposite.
Before finally choosing your
builder, we strongly advise you to ask for quotes and compare them to determine
which professional is best suited to your budget. If several are, the
craftsmanship and construction materials can help you make the best choice.
The site
Site monitoring
When you choose a builder for
your home, several site meetings are scheduled and take place at each bill
payment according to a schedule defined by law:
·
15% at the start of the work
·
25% at the end of the foundations
·
40% after the walls are raised
·
60% when put out of water
·
75% when the air is taken out
·
95% upon completion of equipment, plumbing,
carpentry, and heating work
·
The remaining 5% is paid upon receipt of the
works.
These site meetings are
important. They allow you to check the progress of the work and to ensure that
the site conforms to what was initially planned.
The shell
Earthworks and foundations
Earthwork consists of leveling
the ground and making the trenches to set up the connection with the water,
electricity, gas, and telecommunications networks. These works last longer or
shorter depending on the type of soil. They are carried out more easily in dry
periods and are easier when the soil is compact.
The foundations allow the house
to be perfectly stable on the ground. Different foundation techniques are used
depending on the nature of the soil, the materials, and the construction's
heaviness.
The frame and the roof
The frame supports the roof's
weight and must withstand any additional loads in bad weather (rain, ice,
snow). There are three frames: the traditional frame, the industrial frame (or
truss) and the frame for a flat roof.
Once the frame is finished, the
roof is placed, which can be of different types depending on the local urban
plan, regions, or utility. One can also, for example, consider green roofs or
solar roofs made up of thermal or photovoltaic panels. Once this step is done,
the house is considered to be out of water. Union complex provides the best luxury apartments in Lahore.
Joinery
The installation of joinery
(windows, French windows, and doors) allows putting the house out of air. This
stage generally announces the end of the shell and the finishing work aimed at
making the house habitable.
Handing over the keys
The moment of handing over the
keys allows you to verify that all the work ordered has been completed.
In the event of non-compliance,
you can report it in the acceptance report. If everything is in order and accept
your home as-is, you will have eight days left to pay the remaining 5% to your
home builder. Even after signing and handing over the keys, you will have eight
days left to report a reservation regarding the work.
You can be accompanied by a
construction professional when handing over the keys to identify certain
defects more easily. We recommend never accepting the presence of the expert chosen
by the manufacturer because they are sometimes in cahoots with each other.
Instead, be assisted by a bailiff. And, to make an inventory of the possible
elements to correct, you can ask an architect. It is often better to pay the
fees of these experts to have peace of mind. However, be aware that if you are
accompanied by one of these professionals, you will not be able to benefit from
the eight days delay to make your possible reservations.
Remember that a second RT 2012
certificate is necessary to prove that your finished construction meets these
standards. The declaration attesting to the work's completion and conformity is
also compulsory to notify the town hall of the end of your work.
Finishes
Once at home, the finishes are
your responsibility and allow you to personalize and decorate your interior as
you see fit. You will generally have to perform certain work not supported by
the manufacturer, such as installing the kitchen or that of the roller shutters.
Remember that the layout of the
outdoor spaces is also your responsibility and can be done by a craftsman or by
yourself depending on the remaining budget.
Manufacturers omit to mention
that a certain number of works remain the responsibility of the purchaser upon
delivery. What remains to be done can be costly. Read the notice of your
contract carefully; the arrangements that are not specified to be at your
expense and those for which the expense is not quantified are the
manufacturer's responsibility.